The surveyor should follow these steps when staking curb gutter curb and gutter or barrier wall.
How to stake curb and gutter.
Curb and gutter stakeout for a thoroughfare that will have a curb and gutter these items are usually constructed before the finish grading is done.
The curb constructors obtain their line and grade from offset hubs like those described previously.
48 bull float reinforcing bar cutters 5 cubic foot mixing box with mortar hoe.
Item unit cost quantity line cost.
Prepare and form pour from truck and finish 6 tall by 12 wide curb.
The stake is driven so that it slopes away from the fill or cut and is marked with its horizontal distance left or right from the centerline and the vertical distance from the ground at the stake to the finish elevation.
It also involves placing stakes in the field that mark the location and elevation of proposed grades detention ponds utility structures curb and gutter buildings or any other improvements as shown on the approved engineering design drawing or architectural plans.
Additional cost for 6 tall x 18 wide curb with small gutter feature.
This re i n f o r cement is con tinuous through contraction joints but stops at expan sion joints.
The staking contractor must always consult with the curb gutter curb and gutter or concrete barrier wall contractor and check with engineer for changes to the approved plans before doing any staking or grade computations.
Additional cost for gutter net 6 tall x 24 base for higher volume drainage.
A stake marked c 3 2 48 2 means that the stake is 48 2 feet from the centerline and the ground at the stake is 3 2 feet.
Perimeter form boards and stakes.